FAKTOR-FAKTOR HAMBATAN DALAM PELAKSANAAN PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH

Mukhtarudin Mukhtarudin, M. Isya, Muttaqin Hasan

Abstract


Barriers to construction projects are conditions that can slow down the progress of work. Empirical studies show that there are 40 indicators that hinder project implementation. Most contractor companies, pay less attention to all these obstacles. Contracting companies consider obstacles to be common and natural to find in the project cycle, so that efforts to overcome obstacles are often neglected. This study aims to determine the dominant factors and obstacles that occur in the implementation of road construction projects in Aceh Province. The road construction projects in Aceh Province that are being reviewed are those that use funding sources from the 2018-2022 Aceh Revenue and Expenditure Budget (APBA). This study uses a quantitative method approach through a questionnaire. Respondents were addressed to one of the top management personnel from a road contractor company with medium and large qualifications, namely the project manager, site manager, site engineer, and supervisor. The sampling technique used is simple random sampling, which is random sampling without regard to the proportion of qualification strata of contractor companies, which have been or are currently handling road construction projects. The data analysis technique used was Principle Component Analysis (PCA) with the help of Statistical Product and Service Solution (SPSS) software. The results of the study indicate that the obstacles that occur in the implementation of road construction projects in Aceh Province are five factors, namely managerial, external, financial, consultant, and safety factors with a total variance (percentage of obstacles) of these five factors amounting to 65.395%. The dominant obstacle factor in the implementation of road construction projects in Aceh Province is the managerial factor with a variance of 27.130%.

Keywords


Obstacle; Project; Construction; Road; PCA; Managerial

Full Text:

PDF

References


Anshori M., Iswati, S. 2020. Metodologi penelitian kuantitatif. Airlangga University Press, Surabaya.

Callistus T., Clinton, A. 2016. Evaluating barriers to effective implementation of project monitoring and evaluation in the ghanaian construction industry. Journal Creative Construction. 164 (1), pp. 389-394.

Dandage, R. V., Mantha, S. S., Rane, S. B., Bhoola, V. 2017. Analysis of interactions among barriers in project risk management. Journal of Industrial Engineering International. 14 (2), pp. 153-169.

Darmawi, Muttaqin, Rauzana, A. 2020. Identifikasi faktor-faktor utama penyebab terjadinya keterlambatan waktu penyelesaian pada pekerjaan infrastruktur gedung di Banda Aceh. Jurnal Arsip Rekayasa Sipil dan Perencanaan. 3 (1), pp. 70-79.

Ekowanti, M. R. L., 2017. Kemitraan dalam otonomi daerah. Inteligensia Media, Malang.

Ginting D. P., Pontan, D. 2021. Identifikasi faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi jalan tol. Prosiding Seminar Intelektual Muda, 22 Februari, Universitas Trisakti, Jakarta.

Hair, J. F. 2010. Multivariate data analysis, edisi 7. Pearson Education, New Jersey.

Iqbal K. M., Soekirman, A. 2021. Pemodelan keterkaitan antar faktor kendala penerapan teknologi terbatas (pilot project) bidang jalan melalui penyedia jasa. Jurnal Rekayasa Sipil. 15 (1), pp. 29-38.

Mulyasana, D., Sodikin, O., Kurniawan, A., Haris, A., Djuangsih, T., Hidayatudin, T., Aisah, N. S., Adyawinata, K., Handayani, E., Sadeli, D., Supriastuti, T. 2020. Khazanah pemikiran pendidikan islam dari wacana lokal hingga tatanan global. Cendekia Press, Bandung.

Musafaruddin, Afifuddin, M., Munir, A., 2018. Faktor-faktor penghambat pembangunan layak huni untuk kaum dhuafa di Provinsi Aceh (study kasus: Kabupaten Aceh Utara). Jurnal Arsip Rekayasa Sipil dan Perencanaan. 1 (4), pp. 119-129.

Rossela A., Hudori, M. 2021. Analisis faktor penyebab kendala pada proyek peningkatan jalan (studi kasus jalan simpang marina -simpang base camp Kota Batam). Conference on Community Engagement Project. 1 (1), pp. 67-70.

Sarkar, D., Jha, K. N., Patel, S. 2018. Critical chain project management for a highway construction project with a focus on theory of constraints. International Journal of Construction Management. 21 (2), pp. 1-14.




DOI: https://doi.org/10.24815/jarsp.v5i4.27034

Article Metrics

Abstract view : 0 times
PDF - 0 times

Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 Mukhta rudin, M. Isya, Muttaqin Hasan

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

__________________________________________________________________________________________________________________________________
Jurnal Arsip Rekayasa Sipil dan Perencanaan (Journal of Archive in Civil Engineering and Planning).

Terakreditasi SINTA 4 Berdasarkan Surat Keputusan Direktur Jenderal Riset dan Pengembangan, Nomor: 10/C/C3/DT.05.00/2025

E-ISSN: 2615-1340 P-ISSN: 2620-7567 Organized by Program Studi Magister Teknik Sipil, Fakultas Teknik.

Published by Universitas Syiah Kuala.
Jurusan Teknik Sipil, Fakultas Teknik Universitas Syiah Kuala, Darussalam - Banda Aceh, 23111
Website: http://www.jurnal.usk.ac.id/JARSP/index
Email: jts.mts@usk.ac.id

 Creative Commons License

The Jurnal Arsip Rekayasa Sipil dan Perencanaan (Journal of Archive in Civil Engineering and Planning).
Published by Universitas Syiah Kuala is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on work at http://www.jurnal.usk.ac.id/JARSP/index

 

 VIEW STATS