ANALISA WAKTU DAN BIAYA DENGAN MENGGUNAKAN METODE TIME COST TRADE OFF (STUDI KASUS: PROYEK LANJUTAN PEMBANGUNAN GEDUNG DPRK ACEH TIMUR TAHAP I)

Fazil Fazil, Mochammad Afifuddin, Hafnidar Abd Rani

Abstract

Abstract : Advanced Projects Building DPRK East Aceh Phase I, conducted by PT. Ganis Mandiri. This project began working delay occurs during the 8-day calendar, this is due to delays in the procurement of poles, so that delays in other activities. One way to anticipation by accelerating the method Time Cost Trade Off (TCTO), through the addition of alternative
working hours tested ranging from 1 hour to 4 hours maximum. The research results obtained for overtime several activities, the optimum stage of time and costs obtained in overtime 2 hours on the job aanstamping, couples foundation stone of 1: 4, concrete molds, disassemble mold, concrete, concrete molds, concrete mold, and mold concrete, the obtained optimum time for 160 days at a cost of Rp optimum obtained. 14,961,360,000.00 and the additional cost of Rp. 34,256,000.00.


Keywords : Scheduling, Financing, Crashing, Time Cost Trade Off


Abstrak : Proyek Lanjutan Pembangunan Gedung DPRK Aceh Timur Tahap I, dilaksanakan oleh PT. Ganis Mandiri. Proyek ini terjadi keterlambatan mulai kerja selama 8 hari kalender, hal ini dikarenakan terlambatnya pengadaan tiang pancang, sehingga tertundanya kegiatan yang lainnya. Salah satu cara untuk mengantisipasinya dengan melakukan percepatan yaitu metode Time Cost TradeOff (TCTO), melalui alternatif penambahan jam kerja yang diuji coba mulai dari 1 jam sampai 4 jam batas maksimum. Hasil penelitian ini diperoleh untuk lembur beberapa kegiatan, tahap optimum waktu dan biaya didapat pada lembur 2 jam pada pekerjaan aanstamping, pasangan pondasi batu kali 1 : 4, cetakan beton, membongkar cetakan, cetakan beton, cetakan beton, cetakan beton, dan cetakan beton, dengan diperoleh waktu optimum selama 160 hari dengan biaya optimum diperoleh sebesar Rp. 14.961.360.000,00 dan adanya
penambahan biaya sebesar Rp. 34.256.000,00.


Kata kunci : Penjadwalan, Pembiayaan, Crashing, Time Cost Trade Off

 Keywords

Penjadwalan, Pembiayaan, Crashing, Time Cost Trade Off

 Full Text:

PDF

Refbacks

  • There are currently no refbacks.

ADDITIONAL MENU

  • AIMS AND SCOPE
  • EDITORIAL TEAM
  • REVIEWER
  • PEER REVIEW PROCESS
  • OPEN ACCESS STATEMENT
  • PUBLICATION ETHICS
  • AUTHOR GUIDELINES
  • PLAGIARISM POLICY
  • COPYRIGHT NOTICE
  • AUTHOR FEES
  • CONTACT US
  • USE OF GENERATIVE AI
User

 

Jurnal Teknik Sipil (Journal of Civil Engineering) with E-ISSN: 2502-5295, published by the Department of Civil Engineering, Faculty of Engineering, Universitas Syiah Kuala, was officially designated as a “Nationally Accredited Scientific Journal (Rank 3)” in December 2022.

The accreditation is valid from Volume 10 Number 2 of 2021 until Volume 15 Number 1 of 2026, which will be published in May 2026.

Visitor

 
View My Stats
Journal Content

Browse
  • By Issue
  • By Author
  • By Title
  • Other Journals
  • Categories

Indexed In

 

Logo USK
Department of Civil Engineering, Faculty of Engineering, Universitas Syiah Kuala
Jl. Tgk. Syech Abdul Rauf No.7, Kopelma Darussalam, Kec. Syiah Kuala, Kota Banda Aceh, Aceh 23111
p-ISSN: 2088-9321 e-ISSN: 2502-5295
Email: jurnaltekniksipil@usk.ac.id
 
This work is licensed under an Attribution-ShareAlike 4.0 International