THE CONSIDERATION FACTORS OF WHEEL LOADER PROVISION PROCESS FOR A CONSTRUCTION PROJECT

Mahmuddin - Mahmuddin, Mubarak Mubarak, Ricky Reja Pahlevie

Abstract

Abstract: The completion of a construction project is determined by various factors. One of these factors is related to the adequate availability of equipment resources both in terms of quantity, type, and function. The process for construction heavy equipment provision is generally carried out through the process of purchasing, renting or leasing. The factors that are considered in the supply of equipment are one of the problems that need to be studied further so that the target of effective project implementation can be achieved. Based on these problems, this study was conducted to identify the factors that are considered by contractors in the process of providing equipment in a construction project. This research is focused on the supply of wheel loader heavy equipment by a contractor company in Banda Aceh City. Data collection was carried out using a questionnaire as a research instrument, and involved the participation of 36 contractors with Medium (M1 and M2) and Large (B1) qualifications. The questionnaire instrument is structured into 6 factors consisting of cost, operation and maintenance factors, heavy equipment investment value, risk, equipment specifications and project conditions, and strategy. The process of data analysis applies descriptive statistical methods. The results of the analysis of the contractor's perception data indicate that the strategic factor is the most considered factor by the contractor in the provision of wheel loader heavy equipment. This condition is known from the indication of the average score of 3.11 as the highest value compared to other factors. The strategic factor becomes a top priority for contracting companies in supporting the improvement of the company's image or bona fide, especially when the company offers its services to the construction owner through a tender process.

Keywords: provision, heavy equipment, wheel loader, construction project, Banda Aceh City

 Full Text:

PDF

References

. PMI, 2017. A Guide to The Project Management Body of Knowledge (PMBOK Guide), 6th edition. Pennsylvania: Project Management Institute, Inc.

. Sears, S.K., Sears, G.A., & Clough, R.H., 2008. Construction project management: a practical guide to field construction management, 5th edi-tion. New Jersey: John Wiley & Sons, Inc.

. Nugraha, A.S., and Putranto, L.S., 2019. “The effect of heavy equipment management on the performance of the construction project and the construction company.” IOP Conference Series Materials Science and Engineering. Vol. 650. pp. 012019.

. Shash, A.A., and Ghazi, S., 2003. “Construction equipment management practices of major con-tractors in Saudi Arabia.” Journal of King Saud University - Engineering Sciences. Vol. 1(1). pp. 61-80.

. Gransberg, D.D., Popescu, C.M., & Ryan, R.C., 2006. Construction equipment management for engineers, estimators, and owners. Boca Raton: CRC Press.

. Assauri, S., 2008. Manajemen Produksi Dan Operasi (Edisi Revisi 2008). Jakarta: Lembaga Penerbit Fakultas Ekonomi Universitas Indone-sia.

. Tripoli, Mubarak, dan Shofiasti, Y., 2013. “Faktor-faktor penentu pemenang pelelangan jasa pelaksana konstruksi.” Jurnal Teknik Sipil Universitas Syiah Kuala. Vol. 2(2). pp. 299-300.

. Fachrurrazi, Mubarak, dan Fachreza S., 2015. “Aplikasi software winest terhadap perhitungan rencana anggaran biaya (Studi kasus pembuatan jaringan irigasi Meudang Ara Kecamatan Syam-talira Bayu Kabupaten Aceh Utara).” Jurnal Teknik Sipil Universitas Syiah Kuala. Vol. 3(2). pp. 323-332.

. Mubarak, Bulba A.T., dan Yunita M., 2014. “Studi nilai produktivitas pekerjaan pondasi bored pile.” Jurnal Teknik Sipil Universitas Syiah Kuala. Vol. 3(2). pp. 199-208.

. Rauzana, A., Gunawan, dan Masimin., 2016. “Analisis faktor-faktor penghambat yang ber-pengaruh terhadap waktu proyek irigasi di Provinsi Aceh.” Jurnal Teknik Sipil Universitas Syiah Kuala. Vol. 5(3). pp. 259-268.

. Pham, C.P., Nguyen, P.T., Phan, P.T., Nguyen, Q.L.H.T.T., Le, L.P., and Duong, M.T.H., 2020. “Risk factors affecting equipment management in construction firms.” Risk Factors Affecting Equipment Management in Construction Firms. Vol. 7(11). pp. 347-356.

. Petroutsatou, R., and Giannoulis, P., 2020. “Analysis of construction machinery market: the case of Greece.” International Journal of Con-struction Management, https://doi.org/10.1080/15623599.2020.1741491.

. Pahlevie, R.R., Mubarak, Fachrurrazi, 2021. “Kajian faktor yang dipertimbangkan dalam penyediaan alat berat Excavator di Kota Banda Aceh.” Prosiding Konferensi Nasional Teknik Sipil 15, in press.

. Caterpillar, 2013. Optimize Wheel Loader Per-formance and Productivity. available at: https://www.cat.com/en_US/articles/ci-articles/wl-bucket-guide.html.

. Creswell, J.W., 2009. Research design: Qualita-tive, quantitative, and mixed methods approach, 3rd edition. California: SAGE Publications, Inc.

. de Smith, M.J., 2014. Statistical Analysis Hand-book. Winchelsea: The Winchelsea Press.

. Simatupang, T.M., and Sridharan, R., 2016. “A critical analysis of supply chain issues in con-struction heavy equipment.” International Jour-nal of Construction Management, http://dx.doi.org/10.1080/15623599.2016.1142250.

. Kannan, G., 2011. “Field studies in construction equipment economics and productivity.” Journal of Construction Engineering and Management, Vol. 137(10), pp. 823-828.

. Gransberg, D.D., and O’ Connor, E.P., 2015, Ma-jor Equipment Life-cycle Cost Analysis, Institute for Transportation Iowa State University, Iowa.

DOI: https://doi.org/10.24815/jts.v11i1.23152

Refbacks

  • There are currently no refbacks.

ADDITIONAL MENU

  • AIMS AND SCOPE
  • EDITORIAL TEAM
  • REVIEWER
  • PEER REVIEW PROCESS
  • OPEN ACCESS STATEMENT
  • PUBLICATION ETHICS
  • AUTHOR GUIDELINES
  • PLAGIARISM POLICY
  • COPYRIGHT NOTICE
  • AUTHOR FEES
  • CONTACT US
User

 

Jurnal Teknik Sipil dengan E-ISSN: 2502-5295 yang diterbitkan oleh Jurusan Teknik Sipil, Fakultas Teknik, Universitas Syiah Kuala ditetapkan sebagai Jurnal Ilmiah "TERAKREDITASI PERINGKAT 3" pada Desember 2022.
Masa akreditasi tersebut berlaku mulai dari Volume 10 Nomor 2 Tahun 2021 sampai dengan Volume 15 Nomor 1 Tahun 2026 yang akan diterbitkan pada Mei 2026.

Visitor

 
View My Stats
Journal Content

Browse
  • By Issue
  • By Author
  • By Title
  • Other Journals
  • Categories

Indexed In

 

Logo USK
Department of Civil Engineering, Faculty of Engineering, Universitas Syiah Kuala
Jl. Tgk. Syech Abdul Rauf No.7, Kopelma Darussalam, Kec. Syiah Kuala, Kota Banda Aceh, Aceh 23111
p-ISSN: 2088-9321 e-ISSN: 2502-5295
Email: jurnaltekniksipil@usk.ac.id
 
This work is licensed under an Attribution-ShareAlike 4.0 International